This month HAYSYS has completed the installation, commissioning and Site Acceptance Testing of the final ADL equipment for the England & Wales area at RNAS Yeovilton in Somerset.

The aggressive installation schedule of 19 sites in 19 weeks has been completed absolutely to schedule to the great pleasing of the Ministry of Defence (the customer).

The installation was undertaken with Copperchase Limited providing the installation resource with the commissioning and Site Acceptance Testing being completed by HAYSYS.

The completion of these installations now enables the Auto-Triangulation service provision from NATS in Swanwick.

Dated: September 2007

 